How Do Construction Draws and Inspections Work?
By Andrew J. Liersch III — Founder & CIO, Slingshot Investments. 10+ years in private lending, $500M+ funded. Former Wells Fargo Private Mortgage Banking, Bear Stearns, and Deloitte Consulting.
Short answer: Your construction holdback is released in milestone draws — typically five on an SFR build — and every draw follows the same four-beat rhythm: complete the phase, request the draw, pass the inspection, receive the funds. On private money terms, the inspection-to-wire window runs 24–72 hours. Draws reimburse completed work, so the money flows behind the build, not ahead of it — which is why working capital, documentation habits, and inspection scheduling decide whether your project hums or stalls. Here is the full mechanics, including what inspectors actually verify and the checklist that keeps draws funding on time.
This is the construction-specific companion to our rehab draw schedule guide — the rhythm is the same, but construction draws track build milestones, bigger dollars, and a second layer of inspections the city controls.
The five milestones on a typical SFR build
The approved budget becomes the draw schedule, broken at the natural checkpoints of a build. Using the Del Cerro spec build from our structure article — $850,000 loan, $210,000 land advance at closing:
| Milestone | Work verified | Draw (illustrative) |
|---|---|---|
| 1. Foundation | Grading, footings, slab or stem walls | $120,000 |
| 2. Framing | Structure framed, roof sheathed, windows set | $140,000 |
| 3. Rough MEP | Mechanical, electrical, plumbing roughed in | $120,000 |
| 4. Drywall & exterior | Insulation, drywall, stucco/siding, roofing | $130,000 |
| 5. Finishes & final | Cabinets, flooring, fixtures, certificate of occupancy | $130,000 |
Multifamily builds run the same logic with more milestones — and because the balance steps up as draws fund, this schedule is exactly why as-drawn interest is worth tens of thousands on a construction loan.
The four-beat draw cycle
1. Complete the phase. Draws reimburse finished work — the lender funds what exists, not what is planned. This is the single most important mechanic to internalize: you (and your subs’ payment terms) front each phase, then the draw replenishes.
2. Request the draw. A draw request with the budget line items claimed, photos, and — depending on the lender — invoices or conditional lien releases. Clean requests fund fast; requests that open negotiations do not.
3. Pass the inspection. The lender’s inspector visits, verifies the claimed work against the approved budget and schedule, and signs off. On private money terms this happens in days; bank draw queues are where construction timelines go to die.
4. Receive the funds. Wire within 24–72 hours of a passed inspection on private money terms. Then the cycle restarts on the next phase.
Lender inspections vs. city inspections — two different gates
These get conflated constantly, and the confusion stalls draws. City inspections (foundation, framing, shear, rough MEP, final) are code sign-offs — they gate whether you may legally proceed to the next phase of work. Lender inspections verify completed work against the budget — they gate the money. They are sequenced but separate: a lender’s inspector will want to see the city’s framing sign-off before funding the framing draw, because work the city later makes you open up is not “complete.”
The practical move: schedule city inspections the moment a phase nears completion, not after it finishes. The builders whose draws never stall treat the city inspector’s calendar as part of the construction schedule.
What does a draw actually cost — and what does a slow one cost?
Draw inspections run roughly $200–$300 each — on a five-draw build, call it $1,250, a rounding error in the fee stack. The real cost lives in draw speed: every week a completed phase waits on funding is a week of interest on the full outstanding balance while subs wait to be paid and the site slows. On the Del Cerro numbers, a near-full balance costs roughly $1,700 per week in interest — a three-week bank-style draw delay burns ~$5,000 and, worse, the schedule. Across five draws, that compounding is why experienced builders treat draw speed as a pricing term.
How to never stall a draw
Six habits, all boring, all effective:
- Front-load working capital. Budget the cash to carry each phase before closing — draws reimburse, they do not advance.
- Align sub billing to milestones. Subs invoicing on the same checkpoints the draw schedule uses means paperwork writes itself.
- Photograph everything, continuously. Dated progress photos per line item make inspections confirmations rather than investigations.
- Book city inspections early. The city’s calendar is part of your schedule.
- Keep lien releases current. Where required, collect conditional releases as you pay — not in a scramble at request time.
- Flag change orders before the draw, not during it. Budget reallocations between line items are routine when raised early, and draw-day surprises when not.
Frequently asked questions
How fast do construction draws fund? On private money terms, typically 24–72 hours from a passed inspection. The borrower-controlled part — clean documentation and a ready site — is usually the variable, the same lesson as closing speed.
Who pays for draw inspections? The borrower, per draw — commonly $200–$300 each, set in the loan documents.
Can I take a partial or early draw? Partial draws against partially complete phases are common — the inspector verifies the percentage complete and the draw funds proportionally. Advances ahead of work generally are not how construction lending operates.
What if the inspector and I disagree on completion? It happens, usually on finish-stage percentages. Documentation and photos decide completion percentage along with the budget and common sense approach by the inspector. A second visit costs days; a well-documented request rarely needs one.
Slingshot Investments originates and arranges business-purpose ground-up construction loans on non-owner-occupied residential and commercial real estate. California DRE Broker License #02002790. All loans subject to borrowers and underlying collateral meeting current underwriting criteria. Rates and terms subject to change without notice. This article is general information, not a loan commitment or financial advice.